Barely begun, Porvorim elevated corridor to take longer, cost more

By on September 4, 2024 0 15 Views

The Rs 640-crore elevated highway corridor project in Porvorim is set to face delays and higher costs due to unexpected geological findings. Initial plans for piling up to 20-25m have been revised to 40m after discovering deeper hard rock strata, increasing costs by at least Rs 50 crore and extending the construction timeline.